Station has been designed for 90 sec. peak hour train interval with 70,000 passenger/ hour/direction. Three storey, completely buried station is about 300 meter long and 50 meter wide. Station has been designed as reinforced concrete. Platform is under the ticket hole. The roof is wave formed steel girders standing on the ticket hole beams. The platform level is standing on wall fixed to foundation. The interior and ticket hall have been designed with columns, ribbed beams and slab on the top.
Istanbul Ikitelli Olimpic Village Metro Line Olimpic Stadium Station
Istanbul Metropolitan Municipality/ Gülermak-Doğuş JV
Istanbul / Turkey 2006-2008
• Detail Design and Shop-drawing • Geotechnical Engineering
Railways