Wastewater Treatment
Project
Client
Country Project Period
Services
West Adana Plant designed for year 2010 for an equivalent population of 1.2 million and year 2025 with the population of 1.8 million. East Adana Plant designed for year 2010 for an equivalent population of 0.75 million and year 2025 with the population of 0.97 million. The discharge is estimated to be 398,300 cu.m3/day for year 2010 and 515,940 cu.m3/day for year 2025. Contract value of project is approximately 38 million Euro totally financed by European Investment Bank credit. All the structural design have been based on BS (British Standards).
Adana East & West Wastewater Treatment Plant
Adana Metropolitan Municipality-Water & Sewarage Head Office/Yüksel-Ener-Serco- Vatech Wabag Consortium
Adana / Turkey
1999
• Detail Design and Planning • Geotechnical Engineering